BGSC Club House Extension

BGSC Club House Extension

The beggining of 2014 will see new changes to the Club House at Bartley.

Sandford Construction have been issued a letter of intent which enables them to commence construciton work on the new ladies changing room.

January will see the foundations being constructed.

In February you will see the frame of the building

March will see the internal finishes, chages to the ground floor heating and other work to finish it all off.

The project is part funded by Sport England where we have nearly completed all of the conditions to qualify for the funding e.g. new Lease and Landlords Permission.

If you want to know more, please contact David Jones or Nick Eves (details in DutyMan contacts).

Club Prize Giving
Top Laser sailors are making big improvements
 

Comments 4

David Jones (website) on Saturday, 28 December 2013 15:23
See a visualisation at on YouTube http://www.youtube.com/watch?v=NZB7kOLUO5Q&feature=youtu.be
Paul Archer (website) on Sunday, 09 March 2014 22:37

Works on the way, pictures to follow

Works on the way, pictures to follow
Paul Archer (website) on Friday, 21 March 2014 00:43

Hi All,
works in progress and pictures up on Face Book,

Need to inform you we will not have a kitchen to use over the week end due to the works on the new extraction, cold sandwiches etc. available only.

Hi All, works in progress and pictures up on Face Book, Need to inform you we will not have a kitchen to use over the week end due to the works on the new extraction, cold sandwiches etc. available only.
Paul Archer (website) on Tuesday, 08 April 2014 10:05

“Please be aware the gas will be disconnected next week Tue/wed/Thurs 15/16/17 April which will mean no hot water and reduced menu from the galley whilst the gas meter is moved and the gas main redirected.

“Please be aware the gas will be disconnected next week Tue/wed/Thurs 15/16/17 April which will mean no hot water and reduced menu from the galley whilst the gas meter is moved and the gas main redirected.